RATHBONE PLACE

RATHBONE PLACE

Location: Central London

Client: Great Portland Estates

Contractor: Lend Lease

Project Value: £3.5 Million

Completion: December 2014 – November 2017

System Installed: Tridium / Distech Control Systems

Key Attributes:

  • Shell & Core
  • 25 MCPs
  • 21 MCCs
  • 19 OS Panels
  • 76 Landlords Fan Coil Units (FCUs)
  • 142 Apartments
  • System operates via BACnet TCIP, BACnet MSTP & ModBus
NOVA VICTORIA

NOVA VICTORIA

Location: Victoria, London

Client: Land Securities

Contractor: Mace MEP

Project Value: £8 Million

Completion: February 2014 – Ongoing

System Installed:  Tridium Control Systems

Key Attributes:

  • 50 Power Distribution Panels
  • 170 Control Enclosures
  • 1350 Fan Coil Units (FCUs)
  • 170 Apartments
BBC TELEVISION CENTRE

BBC TELEVISION CENTRE

Location: White City, London

Client: BBC

Contractor: Lend Lease

Project Value: £1 Million

Completion: – –

System Installed: BMS = Trend Control Systems, Fire = ADVANCED / Apollo XP95 Protocol

Key Attributes:

  • Refurbishment of highly intelligent Television Studios 1, 2 & 3
  • New Motor Control Centres
  • Fast Track Programme
MONUMENT PLACE

MONUMENT PLACE

Location: London, UK

Client: Broadgate Estates

Contractor: – –

Project Value: £300,000

Completion: – –

System Installed: Apollo XP95 & ADVANCED Panels

Key Attributes:

  • Fire Alarm consists of 600 Gent devices
  •  A Vesda system is also interfaced to the main system
  • Disabled refuge system consists of Baldwin Boxall Control
  • Panel with 11 outstations
  • 23 Disabled toilet alarms
  • CCTV consists of 13 static and 2 controlled IP Honeywell based cameras
DE VERE GARDENS

DE VERE GARDENS

Location: Kensington, London

Client: – –

Contractor: Sir Robert McAlpine

Project Value: £3.5 Million

Completion: June 2013 – March 2015

System Installed: BMS = Trend Control Systems, Fire = ADVANCED / Hochiki Protocol

Key Attributes: 

  • 6 MCCs Form 2
  • 13 Outstationss
  • 93 Fan Coil Units for Ancillary Areas
  • 97 Apartments a mixture of 1 – 5 bedrooms
  • The system operates via Ethernet, Modbus, Mbus and BACnet.
  • Monitoring of 200 Energy Meters
  • Monitoring of 300 Gas/Water/Electrical Meters
  • L1 Category Fire Alarm Detection
  • Aspirating System
  • Fire Telephone / Disabled Refuge System
20 FENCHURCH STREET

20 FENCHURCH STREET

Location: London, UK

Client: – –

Contractor: Michael Lonsdale Group

Project Value: £1.2 Million

Completion: 2014

System Installed: Tridium Control Systems

Key Attributes:

  • Fast track Fit Out of 9 floors for three different tenants
  • The Fit Out installations were integrated with an existing third party landlord system utilising BACnet
NEWS CORP

NEWS CORP

Location: London Bridge, UK

Client: News UK

Contractor: ISG Plc

Project Value: £1.6 Million

Completion: 2014

System Installed: Distech Control Systems

Key Attributes: 

  • 50 Control Enclosures
  • 1600 Fan Coil Units (FCUs)
HAYS GALLERIA

HAYS GALLERIA

Location: London, UK

Client: – –

Contractor: Overbury

Project Value: £500,000

Completion: September 2013 – April 2014

System Installed: Gent Managed Protocol

Key Attributes:

  • Upgrade Gent System to accommodate refurbishment plans
  • 4 Gent Vigilon Panels added
  • Repeater Panels in each of the three Reception areas
  • 500 Gent S-Quad Detection and Alarm Devices
  • Upgrade of VAV & AHU system in partnership with Lloret Maintenance
PwC, 1 EMBANKMENT PLACE

PwC, 1 EMBANKMENT PLACE

Location: London, UK

Client: Price Waterhouse Coopers

Contractor: Overbury

Project Value: £3.5 Million

Completion: December 2011 – July 2013

System Installed: BMS = Trend / Omron Control System, Fire = Gent Managed Protocol

Key Attributes: 

  • Occupied Building
  • 14 MCCs Form 2
  • 18 SER Room Panels
  • 36 POD MCC Panels
  • 3 MER Room Panels
  • 29 Fire Panels
  • 2 Main Voice Alarm Racks
  • 5000 Field devices
  • Air Sampling
CROYDON CCURV

CROYDON CCURV

Location: Croydon, UK

Client: – –

Contractor: Sir Robert McAlpine

Project Value: £1.1 Million

Completion: March 2011 – January 2013

System Installed: Trend Control Systems

Key Attributes:

  • 90 Fan Coil Units
  • 390 Chilled Beams
  • 10 MCCs Form 4
  • The system operates via Ethernet, ModBus and MBus.
  • High Level Interface
  • HV/LV Electrical Monitoring Interface