CAll Us: 020 8410 4600
PwC, 1 EMBANKMENT PLACE

PwC, 1 EMBANKMENT PLACE

Location: London, UK

Client: Price Waterhouse Coopers

Contractor: Overbury

Project Value: £3.5 Million

Completion: December 2011 – July 2013

System Installed: BMS = Trend / Omron Control System, Fire = Gent Managed Protocol

Key Attributes: 

  • Occupied Building
  • 14 MCCs Form 2
  • 18 SER Room Panels
  • 36 POD MCC Panels
  • 3 MER Room Panels
  • 29 Fire Panels
  • 2 Main Voice Alarm Racks
  • 5000 Field devices
  • Air Sampling
CROYDON CCURV

CROYDON CCURV

Location: Croydon, UK

Client: – –

Contractor: Sir Robert McAlpine

Project Value: £1.1 Million

Completion: March 2011 – January 2013

System Installed: Trend Control Systems

Key Attributes:

  • 90 Fan Coil Units
  • 390 Chilled Beams
  • 10 MCCs Form 4
  • The system operates via Ethernet, ModBus and MBus.
  • High Level Interface
  • HV/LV Electrical Monitoring Interface
THE LANCASTERS

THE LANCASTERS

Location: Hyde Park, London

Client: – –

Contractor: Lorne Stewart

Project Value: £1.5 Million

Completion: – –

System Installed: Tridium / Omron Control Systems

Key Attributes: 

  • 2 MCCs Form 2
  • 8 Outstation Riser Panel
  • Circ 80 Apartments
  • This systems operates via Ethernet
  • High Level Interface to Crestron Systems & VRF Systems Daiken
  • Modbus Room Control
BBC BROADCASTING HOUSE

BBC BROADCASTING HOUSE

Location: Marylebone, London

Client: BBC

Contractor: Lend Lease

Project Value: £6.3 Million

Completion: November 2007 – January 2011

System Installed: Trend Control Systems

Key Attributes:

  • 2000 Chilled Beams
  • Smoke Damper Control System Fully integrated with ventilation systems
  • 84 MCCs Form 2 And Form 4 Type
  • System Resilience Afforded by
  • Dual/duplicated Controllers & Control Devices
  • Virtual Networks Provided with redundant links
  • Managed Network Switches
  • Additional dedicated Networks for essential Systems
  • Automatic transfer switches for essential MCCs & outstation Panels
PARK HOUSE

PARK HOUSE

Location: Mayfair, London

Client: – –

Contractor: Mace MEP

Project Value: £1.2 Million

Completion: – –

System Installed: Tridium / Omron Control Systems

Key Attributes:

  • 12 MCCs Form 4
  • 20 Outstation Riser Panels
  • 450 Office FCUs
  • 45 Apartments
  • Hard Wired or high level to creston apartment automation system
  • Electrical monitoring systems