OLYMPIC STADIUM
Location: Stratford, London
Client: Olympic Delivery Authority
Contractor: Sir Robert McAlpine
Project Value: £1.1 Million
Completion: June 2009 – Jan 2011
System Installed: Trend Control Systems
Key Attributes:
- Distributed MCCs serving localised Plantrooms.
- LTHW & CHW distribution from Park District Systems
- Supplementary Chillers controlled over ModBus Interface
- Localised AHU & Misc Ventilation via BACnet
- Unitary controllers
- Electrical Metering and Monitoring
- FCU & VRF Systems via ModBus & BACnet
- Interface to Park wide Alarm System